(1) Minimum vertical clearance for MVEC's service cable shall be as required by the National Electric Safety Code but in no case less than 12.5' (see NESC Table 232.1).
(2) Point of attachment shall be no less than 12.5' but may have to be higher so MVEC's service cable can maintain a minimum clearance to ground as required by NESC.
(3) The unwrapped portion of the 0service cable at the Member's point of attachment shall be considered part of the drip loop and does not conflict with (1) minimum vertical clearance.
(1) If the base flood level is higher than standard installation height, the meter socket shall be installed at or above the base flood level.
(2) Where meter installation is higher than Standard, Member shall provide and maintain in safe condition an access platform 6' below the top of the meter box. Working area of the platform shall be a minimum of 36" in front of meter box and 15" on either side of meter box. The access platform shall be built to hold 500 pounds per square foot.
Minimum vertical clearance for service cable shall be as required by the National Electric Safety Code but in no case less than 12.5' from the top of the platform (see NESC Table 232.1).